This project is expected to last for about 34 months and will result in a design for the future of Emmet Street that is ready to build. The project has three basic phases – planning, design, and implementation. The timeline below shows major milestones in the project.
- Right-of-Way Acquisition and Utility Relocation: December 2021 – December 2023
- Construction Advertisement: May 2024
- Construction Start: October 2024
Upcoming meetings
DESIGN PUBLIC HEARING for the Emmet Streetscape Project
Design Public Hearing, Emmet Streetscape Project, Dec 3, 2019
State Project: U000-104-297 (UPC 109551); Federal Project: NHPP-5104(256)
Tuesday, December 3, 2019
Informal Plan Review: 5:00 PM to 8:30 PM
Hearing: 7:00 PM to 8:00 PM
Walker Upper Elementary School – 1564 Dairy Rd, Charlottesville, VA 22903